Stegra needs additional capital to complete its new steel plant in Boden and has secured €860 million to invest in port and rail infrastructure as total project costs reach approximately €6 billion.
Stegra has secured €860 million in new financing to invest in port and rail infrastructure for its steel plant in Boden.
“We have completed 60% of the entire project today. We’re making roughly 1% progress per week,” CEO Henrik Henriksson told TT.
The fossil-free steel producer has been hit by several cost increases since the project launched, including the loss of state funding through Industriklivet, inflation, and higher electrical installation costs. The company now must also own infrastructure connected to the plant.
The new investment will cover approximately 15% of the mega project’s costs, currently estimated at around €6 billion.
To provide the best experiences, we and our partners use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us and our partners to process personal data such as browsing behavior or unique IDs on this site and show (non-) personalized ads. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Click below to consent to the above or make granular choices. Your choices will be applied to this site only. You can change your settings at any time, including withdrawing your consent, by using the toggles on the Cookie Policy, or by clicking on the manage consent button at the bottom of the screen.