EcoDataCenter’s first data center was built in Falun. In early 2027, the company’s second site will open in Borlänge. And it doesn’t stop there. The next stop in EcoDataCenter’s expansion is Smedjebacken.

EcoDataCenter started in 2014. The goal was to become the Nordic region’s leading provider of sustainable and secure data center solutions. Areim owns the company. EcoDataCenter is rethinking how it builds and operates data centers in terms of circularity, local impact, energy and sustainability.

The Falun site opened its doors in 2019. It was the first data center of its kind, built with 95 percent solid wood.

“At our site in Falun, we have four data centers in full operation. At the same time, we’re working hard on improvements to make our operations and maintenance even more efficient. We’re also preparing to bring the site’s final two data centers online around the turn of the year 2026–2027,” says Pierre Welander, site manager at EcoDataCenter in Falun.

Bringing the know-how along

Construction of the second site, in Borlänge, began in September 2025. The first data center there is scheduled for completion in early 2027.

“At our site in Kvarnsveden, work is moving full speed ahead on several fronts. We have three data centers under construction in parallel, with a combined capacity of 60 megawatts,” says Johan Appelberg, site manager at EcoDataCenter in Borlänge and continues:

“We now have around 700 construction workers on site, and we’re preparing to welcome about 50 new EcoDataCenter employees in the coming months.”

EcoDataCenter now plans to build a third site in the municipality of Smedjebacken. The company has purchased 52 hectares of land in the Röbacken industrial area. The aim is to start construction as soon as building and environmental permits are in place. EcoDataCenter expects to begin construction in 2027, with the data center potentially operational by 2029.

The Smedjebacken site is expected to create between 125 and 150 permanent jobs. There will be several hundred more jobs during the construction phase.

EcoDataCenter Sweden
Anna Broberg