OPS Hålogalandsvegen, the largest transport infrastructure project ever undertaken in Northern Norway, could be completed in summer 2028, six months ahead of schedule. On 17 november, a quarter of the project, the E10/Rv 85 Kanstadbotn–Langvasseid section, officially opened to traffic.
The new section provides 22.6 kilometres of avalanche-protected and safer road between Lødingen and Sortland. It took around three and a half years to build and was delivered on time.
The entire project, E10/Rv 85 Tjeldsund–Gullesfjordbotn–Langvassbukt, is on track to open in summer 2028, provided progress is not unexpectedly delayed.
“The rapid progress is due to several factors. Statens Vegvesen, The Norwegian Public Roads Administration allowed us to start design work before the contract was signed, the rock conditions in the longest tunnel were good, and our contractor, Skanska, has skilled and efficient staff at every level. Together with the Norwegian Public Roads Administration, we have also found quick solutions to the biggest challenges,” says Fridhild Hjortdahl, CEO of Hålogalandsvegen AS.
The speed limit is now 80 km/h on Rv 85 and 90 km/h on the E10. The 1.4-kilometre Brattfjell Tunnel, a better road surface and higher speeds cut travel time on the section by six minutes.
Nine avalanche embankments, totalling 1,250 metres, also protect the road.
“A fast and safe road that stays open in winter boosts the competitiveness of local businesses, keeps public transport on schedule and reduces the number of accidents. It benefits everyone who travels in the area,” says Ove Myrvåg, Deputy Director General of the Norwegian Public Roads Administration.
Jakob Vorren (Ap), State Secretary at Samferdselsdepartementet, the Ministry of Transport, cut the ribbon with a traditional Sámi knife.
“It is a pleasure to open this part of the PPP project. The development brings southern Troms and northern Nordland closer together. It will strengthen business, emergency preparedness and the development of the entire region for many years to come,” Vorren said in his opening speech.
By 2028, the public-private partnership will have built 82 kilometres of new road. This includes 27 kilometres of tunnels and 20 kilometres of new open-air road. The remaining 35 kilometres follow the existing E10.